8/28/18 @ 3:00 p.m. - Attached are progress updates from the Florida Department of Transportation related to the State Road 200 Widening Project. The reports include information on the first two phases of the project, activities that have taken place since construction began, and activities that are currently underway. If you have any questions, please contact Odette Struys, Information Officer for FDOT, at (904) 360-5582 or via e-mail at [email protected].
0 Comments
8/23/18 @ 9:40 a.m. - Below is lane closure information for the week of August 25-August 31, 2018. NOTE: THERE ARE NO DAYTIME LANE CLOSURES SCHEDULED AT THIS TIME.
SUBJECT: LANE CLOSURE INFORMATION Job Description: SR-200 Reconstruction (W of Rubin Rd. to E of CR 107 Scott Rd.) Financial Project Number: 210712-4-52-01 & 210712-4-56-01 Federal Aid Project Number: 4881064P Contract Number: T2579 County - Section Number: Nassau - 74060 SPECIFIC LOCATION OF THE CLOSURE: Daytime: None at this time. Nighttime:
REASON FOR THE CLOSURE (Type of Construction/Maintenance Activity): Asphalt Paving PROJECT ENGINEER OR CONTACT PERSON AND TELEPHONE NUMBER: ETM Carrie Smithheart, PA Office: (904) 265-3170 Cell: (904) 509-9007 -Sabrina Robertson County Manager's Office 8/16/18 @ 11:00 a.m. - Below is lane closure information for the week of August 18 through August 24, 2018:
SUBJECT: LANE CLOSURE INFORMATION Job Description: SR-200 Reconstruction (W of Rubin Rd. to E of CR 107 Scott Rd.) Financial Project Number: 210712-4-52-01 & 210712-4-56-01 Federal Aid Project Number: 4881064P Contract Number: T2579 County - Section Number: Nassau - 74060 SPECIFIC LOCATION OF THE CLOSURE: Daytime: None at this time. Nighttime:
REASON FOR THE CLOSURE (Type of Construction/Maintenance Activity): Temporary Signals PROJECT ENGINEER OR CONTACT PERSON AND TELEPHONE NUMBER: ETM Carrie Smithheart, PA Office: (904) 265-3170 Cell: (904) 509-9007 -Sabrina Robertson County Manager's Office 8/10/18 @ 5:05 p.m. - Below is lane closure information for the week of August 11 through August 17, 2018. NOTE: THIS INCLUDES DAYTIME LANE CLOSURES ON STATE ROAD 200 FROM 7:00 AM - 5:00 PM ON SATURDAY, AUGUST 11TH.
SUBJECT: LANE CLOSURE INFORMATION Job Description: SR-200 Reconstruction (W of Rubin Rd. to E of CR 107 Scott Rd.) Financial Project Number: 210712-4-52-01 & 210712-4-56-01 Federal Aid Project Number: 4881064P Contract Number: T2579 County - Section Number: Nassau - 74060 SPECIFIC LOCATION OF THE CLOSURE: Daytime:
Nighttime:
REASON FOR THE CLOSURE (Type of Construction/Maintenance Activity): Water Main Tie-In Temporary Signals PROJECT ENGINEER OR CONTACT PERSON AND TELEPHONE NUMBER: ETM Carrie Smithheart, PA Office: (904) 265-3170 Cell: (904) 509-9007 -Sabrina Robertson County Manager's Office 8/2/18 @ 8:40 a.m. - Below is lane closure information for the week of August 4 through August 10, 2018. NOTE: THIS INCLUDES A DAYTIME CLOSURE TO THE EASTBOUND LANE OF STATE ROAD 200 BETWEEN RUBIN DAVIS LANE AND CHESTER ROAD ON SATURDAY, AUGUST 4TH:
SUBJECT: LANE CLOSURE INFORMATION Job Description: SR-200 Reconstruction (W of Rubin Rd. to E of CR 107 Scott Rd.) Financial Project Number: 210712-4-52-01 & 210712-4-56-01 Federal Aid Project Number: 4881064P Contract Number: T2579 County - Section Number: Nassau - 74060 SPECIFIC LOCATION OF THE CLOSURE: Daytime:
Nighttime: None at this time. REASON FOR THE CLOSURE (Type of Construction/Maintenance Activity): Barrier Wall Removal PROJECT ENGINEER OR CONTACT PERSON AND TELEPHONE NUMBER: ETM Carrie Smithheart, PA Office: (904) 265-3170 Cell: (904) 509-9007 -Sabrina Robertson County Manager's Office 7/27/18 @ 2:40 p.m. - Below is lane closure information for the week of July 28 through August 3, 2018. NOTE: THIS INCLUDES DAYTIME LANE CLOSURES FOR SATURDAY, JULY 28TH.
SUBJECT: LANE CLOSURE INFORMATION Job Description: SR-200 Reconstruction (W of Rubin Rd. to E of CR 107 Scott Rd.) Financial Project Number: 210712-4-52-01 & 210712-4-56-01 Federal Aid Project Number: 4881064P Contract Number: T2579 County - Section Number: Nassau - 74060 SPECIFIC LOCATION OF THE CLOSURE: Daytime:
Nighttime: None at this time. REASON FOR THE CLOSURE (Type of Construction/Maintenance Activity): Barrier Wall Repair Fire Hydrant Removal PROJECT ENGINEER OR CONTACT PERSON AND TELEPHONE NUMBER: ETM Kent Ponder Cell: (904) 497-8891 Office: (904) 265-3215 -Sabrina Robertson County Manager's Office 7/19/18 @ 11:20 a.m. - Below is lane closure information for State Road 200/A1A for the week of July 21st through July 27th. NOTE THIS INCLUDES SEVERAL LANE CLOSURES ON SATURDAY, JULY 21ST. JUST A FRIENDLY REMINDER THAT SOME OF THESE AREAS CAN BE AVOIDED BY UTILIZING PAGES DAIRY ROAD, AMELIA CONCOURSE, AND NASSAUVILLE ROAD.
SUBJECT: LANE CLOSURE INFORMATION Job Description: SR-200 Reconstruction (W of Rubin Rd. to E of CR 107 Scott Rd.) Financial Project Number: 210712-4-52-01 & 210712-4-56-01 Federal Aid Project Number: 4881064P Contract Number: T2579 County - Section Number: Nassau - 74060 SPECIFIC LOCATION OF THE CLOSURE: Daytime:
Nighttime: None at this time. REASON FOR THE CLOSURE (Type of Construction/Maintenance Activity): Roadway Improvement of Water Run-off Install Drainage Pipe Locate Water Utility PROJECT ENGINEER OR CONTACT PERSON AND TELEPHONE NUMBER: ETM Kent Ponder Cell: (904) 497-8891 Office: (904) 265-3215 -Sabrina Robertson County Manager's Office 7/17/18 @ 1:55 p.m. - Attached are monthly progress reports from the Florida Department of Transportation as it relates to the State Road 200 Construction Project. The report includes information on activities that have taken place since the project began, as well as activities that took place in June 2018.
If you have any questions, please contact Odette Struys, Information Officer for FDOT, at (904) 360-5582 or via e-mail at [email protected]. -Sabrina Robertson County Manager's Office 7/6/18 @ 8:40 a.m. - Below is lane closure information for the week of July 7 through July 13, 2018. NOTE: THIS INCLUDES A DAYTIME LANE CLOSURE ON SATURDAY, JULY 7TH FROM 7:00 A.M. - 5:00 P.M. TO THE WESTBOUND RIGHT LANE OF STATE ROAD 200/A1A BETWEEN O'NEIL SCOTT ROAD TO BLACKROCK ROAD.
SUBJECT: LANE CLOSURE INFORMATION Job Description: SR-200 Reconstruction (W of Rubin Rd. to E of CR 107 Scott Rd.) Financial Project Number: 210712-4-52-01 & 210712-4-56-01 Federal Aid Project Number: 4881064P Contract Number: T2579 County - Section Number: Nassau - 74060 SPECIFIC LOCATION OF THE CLOSURE: Daytime:
Nighttime: None at this time. REASON FOR THE CLOSURE (Type of Construction/Maintenance Activity): Attenuators and Moving Barrier Wall PROJECT ENGINEER OR CONTACT PERSON AND TELEPHONE NUMBER: ETM Carrie Smithheart, PA Office: (904) 265-3170 Cell: (904) 509-9007 -Sabrina Robertson County Manager's Office 7/5/18 @ 2:15 p.m. - The Florida Department of Transportation will be hosting an Open House on Tuesday, July 17, 2018 from 4:30 -6:30 p.m. to discuss the Amelia Island Resurfacing Project. This project will provide the segment of State Road 200/A1A from the Thomas J. Shave Bridge to Centre Street with newly resurfaced pavement, repairs to the curb,medians and sidewalks, along with a few other upgrades and modifications. The project is expected to begin this summer. The Open House will be held at the Nassau County Chamber of Commerce located at 961687 Gateway Boulevard, Suite 101G, Amelia Island, FL 32034. Attached is the flyer containing additional information. If you have any questions, please contact Odette Struys, Public Information Officer for FDOT, at (904)360-5348 or via e-mail at [email protected]. -Sabrina Robertson County Manager's Office |